NameCompany
Linux Foundation
Rajesh Krishnan Peraton Labs
Lincoln Thurlow University of Southern California, Information Sciences Institute
Ranny Haiby LF
David McBride LF
Brandon Wick Aarna
Yogendra Pal Aarna Networks
Yow-Jian Lin Peraton Labs
















                        

Agenda:

...

    • Initial PoC:
    • Kaloom lab- VMs built - Risk
      • Do we have a risk? What is the mitigation?
    • Potential Hex Five sub project - Cesare/Rajesh
      • Investigative meeting took place between Peraton and Hex Five (Cesare).
      • Next Step- Hex Five to come back with a proposal
    • Next Steps:
      • Rajesh- Set back. Need to revaluate camera wrt memory
        • Options
          • Potential Shift to use a low end sensor (ex: temperature sensor)Find camera that requires less memoryweather sensor instead of camera
      • Aarno Labs has implemented SEDIMENT for a government funded project
        • Can they provide a demo or overview to the community? This is a government funded project, and is looking into what can be shared with this community
      • Looking to create an easy to use guidebook (Raj)
        • Would have to go through DARPA Public Release process
        • Aarno Labs- an MIT spin-off. Provides security for (currently) Java script. Whereas KubeArmor protects at the container level, Aarno protects at the Java script program level. SEDIMENT offers them an alternative where they may not be deploying on SGX (Software Guard Extensions). Contact Eric and Jeff Perkins also on SEDIMENT project. Raj to make introduction. Presented on Sept PI meeting.
      • Identify and develop a security Use Case

...

    • Three use cases will have separate services associated
    • What orchestrator will/can be used?
      • potential to duplicate Simplified E2E Network Slicing (Aarna) using EMCO
        • Aarna confirms all Simplified network slicing solution will be open source and NDA will not be required.
        • License - Apache 2
      • potential to leverage Wavelabs slicing using EMCO
    • ICCCN paper: ICCCN_2023_paper_187.pdf
    • Code repository (https://pulwar.isi.edu/sabres/cbs/cbs) that was used during the last government demonstration.  This is the initial code base (src directory), which will not be the final product (as this version only works on 2-3 variables, rather than arbitrary).  This code was used to replace ETSI's OSM's PLA module (using minizinc constraint solver) with CBS [https://osm.etsi.org/gitlab/osm/pla].
    • Lincoln tried setting up EMCO using documentation and it failed to come up.
    • SD-Core setup at ICI
    • Next Steps:
      • Open question on open sourcing SABREs (university policy) - still open - Risk
      • Replicate Simplified Slicing demo locally in ISI lab (Lincoln)
      • Debug the environment (Lincoln)
      • Setup SD-Core at ICI (demonstrate slicing using SD-Core)
        • rewriting parts of the UPF to integrate SABREs code
      • Set up a drop-in replacement for the current slicing algorithm with CBS algorithm (Lincoln)
      • Leverage UNH and Kaloom. Ganesh and Lincoln?

...

    • Scope-
      • use ONAP SMO to exercise gNodeB. Showcase RAN connectivity (O1 interface)
      • Showcase orchestration
      • Connect gNodeB
        • Mitigation- UNH can host core but has no resources to implement; Yogen can implement
      • Potential reference point/tie-in with ORAN-SC
    • Requirements/Goals
      • Showcase RAN connectivity (O1 interface)Demonstate connectivity and orchestration
      • exercise Amarisoft gNodeB (UNH)
      • Demonstate core connectivity
      • Stretch goal- tie-in with ORAN-SC
      • Stretch goal - Showcase RAN connectivity (O1 interface). OAI not ready with O1 interface
    •  Resources-
      • Aarna Networks
      • UNH - gNodeB. Note; gNodeB is T&M gear and will need to be shared among projects.
      • Kaloom - Core- Risk
        • UNH has space for a core but no people resources. Potential for a 5G SBP  resource to help. 
          • Mitigation- Yogen can implement the core at UNH
    • Next Steps-
      • Edit two config files with ansible to orchestrate the on-boarding process for the Bring up OAI core and orchestrator with Amarisoft gNodeB - YogenUNH lab
        • Create Ansible template / tasks that would deal with the gNodeB - Lincoln/Yogen
        Onboard core - Yogen
        • Bring uo OAI core at UNH using the orchestrator
      • LaaS booking, extend the booking to last longer than 21 days - ping lincoln by email.


Simplified E2E Network Slicing (Aarna)

...

Edge Site Selection and Placement (Equinix) - On Holdhold

    • From June D&TF - Call to action: What is current state of edge site selection and where does it need to evolve (future state)?
    • Tie-in with simplified slicing (Aarna)
    • Edge definition talk from the LF? Twitter? LF Edge Taxonomy. https://hubs.la/Q01RnPZh0
    • Next Steps
      • Proposal to pause, and focus on E2E slicing
      • Slice selection within edge placement - Yogen

...

  • LFN Developer & Testing Forum (Budapest, Hungary) this is an on-site event. 

    • November 13-16, 2023
    • Registration is open and free
      • Submit Visa letter requests (if needed) ASAP
    • Topic Submissions
    • November D&TF Planning
      • Opportunities-
        • Potential for ONAP SMO session (with OAI)
        • End-to-End deployment of an eBPF-based Free5GC Core - Use Case - addresses sensitive workload requirements (finance, government, etc.), thought workload segmentation.
          • first, generic capabilty of secure workloads
          • then show how secure workloads of eUPF in 5G Use case can be accomplished
        • 5G SBP Library - LJ
          • What is the 5G SBP Library? (mind maps). Inform users/readers and be able to take the next steps with find the right capability and use the information. Different capabilities to put together 5G services
          • High level overview of each project currently in development (SABREs, SEDIMENT, ORAN SMO, Edge site selection).
            • Input will be requested input from the project leads
          • How to get involved
          • Process- how to submit a proposal
          • Build out talking points; work with Muddasar

...

  • Off-week working group meeting
    • Topic: D&TF planning?
    • project deep dive - SEDIMENT Security Use Case?
    • Work with OAI
  • Bi-weekly Status Meeting

...