Attendees
Absent (but included here so they receive the meeting minutes):
- xyz
Open Action Items
Task report
Looking good, no incomplete tasks.
Agenda & Minutes
Standing Items:
- Review Open Action Items (from weekly meeting minutes)
- Review Open Issues in Gitlab
Topics for this week:
- Review of Anuket Assured plan (plan attached below)
- General progress/status check
- We need volunteers who can support as Workstream Leads. Current volunteers are:
- Prerequisites / Blockers: Scot & Kodi
- Anuket Certified Lab: Lincoln
- Anuket Certified R2 CNF: Vacant
- We need volunteers who can support as Workstream Leads. Current volunteers are:
- Prerequisites Status
- Scot/Kodi
- Anuket Certified Lab Status
- Lincoln
- Anuket Certified R2 CNF Status
- Olivier presented (Anuket R2 CNF Discussion.pptx ) to the Anuket Technical Meeting (attending was Gergely and Cedric). Meeting notes are here: Anuket Weekly Technical Discussions - 2023.03.08 - Anuket - Anuket
- Cedric took an action to review the requirements/tests for Nile release
- Olivier presented (Anuket R2 CNF Discussion.pptx ) to the Anuket Technical Meeting (attending was Gergely and Cedric). Meeting notes are here: Anuket Weekly Technical Discussions - 2023.03.08 - Anuket - Anuket
- Anuket (Nile release)
- Background information on requirements for R2 CNFs (workloads): anuket-specifications/chapter04.rst at master · anuket-project/anuket-specifications (github.com)
- Work is still ongoing between CVC and the Anuket project in order to understand: a) Which requirements will be used for a version 1.0 of the badge. b) If all tests for those requirements exist and are ready to be utilized.
- General progress/status check