Page is in draft.


The first XGVela release plans to be delivered in 2022. Duration will last for around 6 months.


EventDatesRelative DatesStart Relative DatesDescription
Release Start2022-06-21Start DateStart Date

Declare Intention: Submit Project Proposal (for new projects) and Project Plan in wiki under projects.

Project Proposals

Initial Checkpoint2022-07-05Start Date + 2 WeeksStart Date + 2 WeeksInitial Checkpoint. All Projects must have completed project plan and get the plan reviewed under TSC meeting.

Integrated Projects deadline

(Optional for first release)

2022-07-19Initial Checkpoint + 2 WeeksStart Date + 4 WeeksAs this is the first release, this is the period for each project to confirm the version of the projects they want to integrate.  Deadline for the confirmation. (For release 1, there is no previous version to be integrated, each project would list their own integration reliance and make sure the projects to be integrated can work normally)
Project's tool preparation (Optional)2022-07-19Initial checkpoint + 2 weeks

Start Date + 4 weeks

Release manager prepare development tools for project who requires it, including github repo, meeting bridge, jenkins silo, Jira.
Middle Checkpoint2022-09-27Project's tool preparation + 10 weeksStart Date + 14 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze2022-10-25Middle checkpoint + 4 WeeksStart Date + 18 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint2022-11-15Code Freeze + 3 WeeksStart Date + 21 WeeksFinal Checkpoint for all project. Documentation should be completed before final checkpoint.
Formal Release2022-11-29Final checkpoint + 2 WeeksStart Date + 23 WeeksFormal Release for XGVela.

How to prepare key contents of each event? Please go to Release Process.