2022  Trial Scheme. Apply to review on TSC meeting 2022-01-25. 

XGVela, the telecom cloud native PaaS platform project, is a loosely coupled project. Each of Telco PaaS capabilities and Adaptation Layer capabilities, which XGVela plans to deliver, can either be treated as a group of independent projects, or be combined and treated as one project. The decision will be made as the beginning of project lifecycle by Project’s Committer. And the projects are primaryly self-managed projects.

For each project, the Project’s Committer make all decisions about Releases of that Project. However, following the Release Process is required. The purpose of the Release Process is to insure openness and maximum opportunity for participation. The idea is to have a simple, clear, public declaration of what a project intends to do and when, and what was actually done in a release cycle.

EventDescriptionDateDetailed  Requirements
Release Start

The start date of project's release.

Start date
  • Project's Committer should prepare initial Release Plan and post the plan details on project's independent webpage.
  • Send initial Release Plan (link or material) to tsc mailing list, and apply for TSC review.
  • TSC will add shcedule about initial release plan review to the following TSC meeting. Meeting invitation will be send to Project's Committer.
Initial CheckpointTSC review Release plan provided by Project's committer.Start date + 1 or 2 weeks
  • Project's committer will present to TSC members about initial Release Plan.
  • TSC members will provide suggestions.
  • Project's committer and TSC member will discuss together and reach on agreement about a fixed Release Plan. 
  • Meeting minutes should be taken. Release Plan should be updated according to meeting result.
Middle Checkpoint

Optional.

TSC review release progress provided by Project's committer.

Start date + (1/2)*Release duration

Release duration = release end date - start date

  • Projects committer can apply for middle release review by sending email to tsc mailing list.
  • Project's committer will present to TSC member about release progress. Presentation materials are optional.
  • Tiny adjustment of release plan are allowed.
  • Meeting minutes should be taken. Release Plan should be updated according to meeting result explicitly under “Mark-up” model.
Formal ReleaseTSC review Release contents provided by Project's committer.Release end date
  • Project's committer should prepare Release Contents and post detials on on project's independent webpage.
  • Project's committer will present to TSC members about release contents.
  • TSC members will comment on release content.
  • Meeting minutes should be taken.
Release MarketingPrepare release marketing materials.Release end date + 2 weeks
  • Project'c committer and self-nominated TSC members will prepare marketing materials for the release.
  • Contact LFN marketing manager for PR.