NOTE: This is the weekly technical deep dive call to prep the latest version of the 5G Cloud Native Network Demo for ONE Summit 2021, Oct 11-12. If you would like the meeting invite, please email bwick@linuxfoundation.org and lilluzzi@linuxfoundation.org.

...

tatus Check / Open Questions

Slicing:

09/14:  Need Hanen/team to help troubleshoot.


Yogendra Pal  12:54 AM
@Hanen Garcia Need your help. Login into MTL cluster is not happening any more (oc login -u kubeadmin -p f4swJ-AaAA3-c5x8D-rsrbA https://api.cluster01.mtl.kaloom.lab:6443). Error: The connection to the server oauth-openshift.apps.cluster01.mtl.kaloom.lab was refused - did you specify the right host or port?Hanen Garcia  6:53 AM

...

9/7: Jacobus. Running ping on trusted, not seeing traffic on untrusted side. Jacobus, Raja, etc will have a separate working session. 


RAN:

09/14:  Cobus- hardware has arrived. Will update the team on config, HW, cabling, radio documentation. Fiber will be run between the different equipment in the facility.


09/02 Sveto: We have installed the master clock. It is connected with fiber to a NIC (Intel XXV710) in the same server you’re using. The management port of the clock should be reachable on 10.198.7.197. We kept the default admin user and password. 

...

  • Video - Due  
    • Shoot various video (approx 5 minute in total)
      • Slicing - Yogendra. (Amar) - ONAP side of slicing can be captured.
      • RAN - CU/DU config - Amit, L1 integration with CU/DU
      • Radio - photos or video of the lab/cage
      • Rabaca dashboard - 
    • Voice over - Heather/Amar
    • Edit video - Louis/Brandon have lead
  • Slideware  
    • Animation
    • 5G Cloud Native Topology diagram. Other diagrams available? Jamie has a Network diagram
  • Build Guide

...

Final Testing and Configuration:  -  (Sept 10 ambitious, keep for now to keep things moving)

Collateral Development: 13  -  

  • Slideware/script/video(s)/animation 

...

  • REMINDER: "Document as you Build" approach would help expand our options.
  • Video Capture platform options (Louis)- (Loom, Ezvid, FreeCam)
  • ONE Summit Questions: 1) there is no demo during Heather’s keynote, correct. Brandon explained the ONE Summit logistics plan.