Goals

  1. Develop robot plugin to integrate with VTP which is similar to cmd, http and snmp plugin.
  2. Integrate ETSI NFV APIs conformance test cases to VTP
  3. Verify all ETSI NFV APIs conformance test cases.

Tasks

#

Activity

Due Date

Status

1.

Develop robot plugin to VTP

2020-7- 10

Completed

2.

Adding SOL005 ETSI NFV APIs conformance test cases

2020-8-1 

Completed

3.

Develop NFVO simulator to verify SOL005 test cases

2020-8-21 

PENDING

4.

Adding SOL003 ETSI NFV APIs conformance test cases

2020-9-20 

Completed

5.

Develop VNFM simulator to verify SOL003 test cases

2020-10-2

PENDING

6.

Adding SOL002 ETSI NFV APIs conformance test cases

2020-10-22

Completed

7.

Develop VNF simulator to verify SOL002 Test cases

2020-11-10

PENDING

8.

User guide or other development delivery documents

2020-11-13

PENDING

Deliverables

  • Development code for Robot plugin
  • ETSI NFV APIs conformance test cases which are available in VTP
  • SOL005/003/002 simulator for verifying ETSI NFV APIs conformance test cases which are available in VTP.
  • User guide or other development delivery documents

Milestones

Week 3(6.1-6.19)

  •  General understanding and local set up of VTP
  •  General understanding the existing plug-in(cmd, http and snmp plugin) integration methods in CLI

Week 6(6.22-7.10)

  •  Begin to develop robot plugin in VTP(50% complete)
  •  Finish robot plugin development in VTP(100% complete)

Week 12(7.13-8.21)

  •   General understanding of SOL005 ETSI NFV APIs conformance test cases
  •  Adding SOL005 ETSI NFV APIs conformance test cases to VTP (100% complete)
  •  Finish NFVO simulator to verify ETSI NFV APIs conformance test cases which are available in VTP

Week 18(8.24-10.2)

  • General understanding of SOL003 ETSI NFV APIs conformance test cases
  •  Adding SOL003 ETSI NFV APIs conformance test cases to VTP (100% complete)
  • Finish VNFM simulator to verify ETSI NFV APIs conformance test cases which are available in VTP

Week 24(10.5-11.13)

  • General understanding of SOL002 ETSI NFV APIs conformance test cases
  • Adding SOL002 ETSI NFV APIs conformance test cases to VTP (100% complete)
  • VNF simulator to verify ETSI NFV APIs conformance test cases which are available in VTP.
  • Deliver user guide or other development documents

Evaluation Criteria

  • 1st Evaluation (end of week 6):  Good understanding of project goal, VTP framwok, plugin development method .Finish robot plugin development in VTP

  • 2nd Evaluation (end of week 12):   Adding SOL005 ETSI NFV APIs conformance test cases to VTP  and using NFVO simulator to vertiy the test cases which are available in VTP

  • 3rd Evaluation (end of week 18):  Adding SOL003 ETSI NFV APIs conformance test cases to VTP and using VNFM simulator to vertiy the test cases which are available in VTP

  • Final Evaluation (end of week 24):  Adding SOL002 ETSI NFV APIs conformance test cases to VTP and using VNF simulator to vertiy the test cases which are available in VTP . Deliver user guide or other development documents

Project Results/Outcome

 