This page is now draft release schedule for 2023. Initial time plan will be created.
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | Start Date | Start Date | Declare Intention. New project proposal + Existing project's release plan | |
Initial Checkpoint | Start Date + 2 Weeks | Start Date + 2 Weeks | Initial Checkpoint. Project proposal review and release plan review | |
Integrated Projects deadline | Initial Checkpoint + 2 Weeks | Start Date + 4 Weeks | Previous release or other project integration for development preparation. | |
Middle Checkpoint | Integrated projects deadline + 8 weeks | Start Date + 12 Weeks | Middle Checkpoint for progress of all Projects. | |
Code Freeze | Middle checkpoint + 4 Weeks | Start Date + 16 Weeks | Code freeze for all Projects - cut and lock release branch. | |
Final Checkpoint | Code Freeze + 4 Weeks | Start Date + 20 Weeks | Final Checkpoint for all project. Documentation should be completed before final checkpoint. | |
Formal Release | Final checkpoint + 2 Weeks | Start Date + 22 Weeks | Formal Release for XGVela. |