This page is now draft release schedule for 2023. Initial time plan will be created.


EventDatesRelative DatesStart Relative DatesDescription
Release Start
Start DateStart Date

Declare Intention.

New project proposal + Existing project's release plan

Initial Checkpoint
Start Date + 2 WeeksStart Date + 2 Weeks

Initial Checkpoint.

Project proposal review and release plan review

Integrated Projects deadline


Initial Checkpoint + 2 WeeksStart Date + 4 WeeksPrevious release or other project integration for development preparation.
Middle Checkpoint
Integrated projects deadline + 8 weeksStart Date + 12 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze
Middle checkpoint + 4 WeeksStart Date + 16 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint
Code Freeze + 4 WeeksStart Date + 20 WeeksFinal Checkpoint for all project. Documentation should be completed before final checkpoint.
Formal Release
Final checkpoint + 2 WeeksStart Date + 22 WeeksFormal Release for XGVela.