EventDatesRelative DatesStart Relative DatesDescription
Release Start2022-06-21Start DateStart Date

Declare Intention: Submit Project Proposal (for new projects) and Project Plan .

For new projects whose feature not covered in Projects page, submit Project Proposals in wiki under projects.

For potential projects whose features already discussed as release 1 candidate in Projects page, submit  Project Proposals and clarify covered features in Projects page.

Initial Checkpoint2022-07-05Start Date + 2 WeeksStart Date + 2 Weeks

Initial Checkpoint. All Projects must have completed project

plan and get the plan reviewed under TSC meeting.

proposal.

For new projects whose feature not covered in  Projects page, apply for TSC review through xgvela-tsc@lists.xgvela.org . Relationship with existing features and projects should be clarified.

For potential projects whose features already discussed as release 1 candidate in Projects page, send email of project proposal to xgvela-tsc@lists.xgvela.org

Integrated Projects deadline

(Optional for first release)

2022-07-19Initial Checkpoint + 2 WeeksStart Date + 4 WeeksAs this is the first release, this is the period for each project to confirm the version of the projects they want to integrate.  Deadline This is the deadline for the confirmation. (For release 1, there is no previous xgvela version to be integrated, each project would list their own integration reliance and make sure the projects to be integrated can work normally)Project's tool preparation (Optional)2022-07-19Initial checkpoint + 2 weeks

Start Date + 4 weeks

Release manager prepare development tools for project who requires it, including github repo, meeting bridge, jenkins silo, Jira.
Middle Checkpoint2022-09-27Project's tool preparation Integrated projects deadline + 10 weeksStart Date + 14 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze2022-10-25Middle checkpoint + 4 WeeksStart Date + 18 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint2022-11-15Code Freeze + 3 WeeksStart Date + 21 WeeksFinal Checkpoint for all project. Documentation should be completed before final checkpoint.
Formal Release2022-11-29Final checkpoint + 2 WeeksStart Date + 23 WeeksFormal Release for XGVela.

...