2022  Trial Scheme. Apply to review Reviewed on TSC meeting 2022-02-08. 

...

EventDescriptionDateDetailed  Requirements
Release Start

The start date of project's release.

Start date
  • Project's Committer should prepare initial Release Plan and post the plan details on project's independent webpage.
  • Send initial Release Plan (link or material) to tsc mailing list, and apply for TSC review.
  • TSC will add schedule about initial release plan review to the following TSC meeting. Meeting invitation will be send to Project's Committer.
  • For new projects, project proposal should be provided along with project's release plan.
Initial CheckpointTSC review Release Plan provided by Project's committer.Start date + 1 or 2 weeks
  • Project's committer will present to TSC members about initial Release Plan (and with project proposal).
  • TSC members will provide suggestions.
  • Project's committer and TSC member will discuss together and reach on agreement about a fixed Release Plan. 
  • Meeting minutes should be taken. Release Plan should be updated by Project's Committer according to meeting result.

Middle Checkpoint

(Optional)

TSC review release progress provided by Project's committer.

Start date + (1/2)*Release duration

Release duration = release end date - start date

  • Projects committer can apply for middle release review based on project's own condition by sending email to tsc mailing list.
  • Project's committer will present to TSC member about release progress. Presentation materials are optional.
  • Tiny adjustment of release plan are allowed.
  • Meeting minutes should be taken. Release Plan should be updated according to meeting result explicitly under “Mark-up” model.
Formal ReleaseFinal CheckpointTSC review Release Review provided by Project's committer.Release end date - 1 or 2 weeks
  • Project's committer should prepare Release Review and post detials on on project's independent webpage.
  • Project's committer will present to TSC members about Release Review.
  • TSC members will comment on release content. Meeting minutes should be taken.
Formal Release
Release end date
Release MarketingPrepare release marketing materials.Release end date + 2 weeks
  • Project's committer and self-nominated TSC members will prepare marketing materials for the release.
  • Contact LFN marketing manager for PR.

...

ContentsDescription
Project name/
Release Accomplishment (Important)This covers the major accoplishment of the release, such as delivered feature, budfixes, pased test, delivered documentation, etc.
Summary of Outstanding AccomplishmentHighlight outstanding accomplishment and explain its benefit.
Delta between planend planned and actual accomplishement (Important)List the difference between the planned accomplishement in Release Plan and the actual accomplement.
Plans for Next Release (if any)Brief description of plans for next release.

...