This page is now draft release schedule for 2023. Initial time plan will be created.
Initial Checkpoint | Event | Dates | Relative Dates | Start Relative Dates | Description |
---|
Release Start | 2023-07-11 | Start Date | Start Date | Declare Intention. |
New project proposal + Existing project's release plan
For new project: - Submit a new project proposal following the steps on Project Proposals. Contents about "Release Planning & Release Notes" is required.
- Review candidate features in Projects page and clarify the whether the features new project wants to deliver is within the list or out of the list.
- Review delivered features of Approved Projects to avoid duplication.
For existing project: - Update "Release Planning & Release Notes" section in your project page by adding features to be delivered in new release on the section top.
|
Initial Checkpoint | 2023-07-25 |
Start Date + 2 Weeks | Start Date + 2 Weeks | Initial Checkpoint. |
Project proposal review and release plan review- All Projects must have completed project proposal or new release plan.
- All projects' PTL should send email to xgvela-tsc@lists.xgvela.org get rlease plan publicly reviewed.
- PTLs of new projects will be invited to TSC meetings for project introduction. TSC will vote for new project approval.
|
Integrated Projects deadline | 2023-08-15 | Initial Checkpoint + |
2 4 Previous release or other project integration for development preparationDependency check. - Each project prepares foundamental environment for developing in this release (icluding but not limited to lab, server, software, etc.).
- Projects who have reliance on XGVela approved project can clarify the software and environment requriements. Instructions or environment support is recommended to be provide by approved projects team.
|
Middle Checkpoint | 2023-10-10 | Integrated projects deadline + 8 weeks | Start Date + |
12 13 Weeks | Middle Checkpoint for progress of all Projects. |
Code Freeze | 2023-11-14 | Middle checkpoint + |
4 16 18 Weeks | Code freeze for all Projects - cut and lock release branch. |
Final Checkpoint | 2023-12-12 | Code Freeze + 4 Weeks | Start Date + |
20 22 Weeks | Final Checkpoint for all project. Documentation should be completed before final checkpoint. |
Formal Release | 2023-12-26 | Final checkpoint + 2 Weeks | Start Date + |
22 24 Weeks | Formal Release for XGVela. |