This page is now draft release schedule for 2023. Initial time plan will be created.


EventDatesRelative DatesStart Relative DatesDescription
Release Start
Start DateStart Date

Declare Intention.

New project proposal + Existing project's release plan

For new project:

  1. Submit a new project proposal following the steps on Project Proposals. Contents about "Release Planning & Release Notes" is required.
  2.  Review candidate features in Projects page and clarify the whether the features new project wants to deliver is within the list or out of the list.
  3. Review delivered features of Approved Projects to avoid duplication.

For existing project:

  1. Update "Release Planning & Release Notes" section in your project page by adding features to be delivered in new release on the section top.
Initial Checkpoint
Start Date + 2 WeeksStart Date + 2 Weeks

Initial Checkpoint.

Project proposal review and release plan review
  1. All Projects must have completed project proposal or new release plan.

All projects apply for TSC review through xgvela-tsc@lists.xgvela.org

Integrated Projects deadline


Initial Checkpoint + 2 WeeksStart Date + 4 WeeksPrevious release or other project integration for development preparation.
Middle Checkpoint
Integrated projects deadline + 8 weeksStart Date + 12 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze
Middle checkpoint + 4 WeeksStart Date + 16 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint
Code Freeze + 4 WeeksStart Date + 20 WeeksFinal Checkpoint for all project. Documentation should be completed before final checkpoint.
Formal Release
Final checkpoint + 2 WeeksStart Date + 22 WeeksFormal Release for XGVela.