Goals

This project will focus to address the remaining Security requirements defined by the ONAP SECCOM Community based on JIRA Backlog

Perform the necessary migration/upgrade to packages according to the SDC security vulnerability report

Tasks

(Due dates are roughly estimated and are subject to change ±)
#ActivityDue DateStatus
1.

Set up SDC local development environment and run Sanity tests. Get familiar with SDC components and understand he interaction among them  

 

2.Upgrade maven dependencies to more recent versions so they don’t include security vulnerabilities

 

3.Generate certificates with AAF in deploy time and integrate them

 

4.Getting CII badges (passing/silver/gold)

 

5.Fixing security tickets and ONAP JIRA Security Issues (OJSI)

 

6.Bounce checking special characters for SDC APIs

 

7.Migrating Junit 4 to 5

 

8.Java 11 migration

 

9.Complete pending tasks + Summary report 

 

Implementation

Milestones

Week 6

Week 12

Week 18

Week 24


Mentee: Amir Mohamad