The 10/16 meeting was reserved for a formal RI kickoff.
Refer to RI meeting minutes for complete list of discussion topics covered on 10/16: CNTT - RI - 01
For RC, status is as follows:
RI Labs have been secured: Intel Labs POD10 (PoC) and End-State POD15
AirShip installations are starting this week. Target is to complete the installs by end of this week. Sridhar from Spirent is leading the installations.
Access has been processed, and Mike Fix was able to successfully connect to both Labs
Cedric from Orange requested access today (10/16). Cedric did confirm there are existing test suites available to run post-AirShip deployment to verify installation and deployment.
Next Steps: See below for details. BLUF, 1) Complete AirShip deployment, 2) Tune manifest if needed, 3) Align RC WS team on deliverables, 4) continue on WS issues
Details
RI Labs - Intel Lab
POD10 (CNTT RI PoC)- will be used for initial install of OS via AirShip
Clarification needed as to why we can start on 15 in parallel or first → for PoC, installation validations, not anticipated to impact POD15 delivery cycle