Meeting Logistics:
- Every Wed at UTC 13:00-13:30 | https://zoom.us/j/694881078
- Antitrust
- Email dsitros
Attendee List:
- Qiao Fu (china Mobile)
- Michael Fix (AT&T)
Goals of Meeting
- Status
- Labs & Next Steps (POD10/15)
- HDV
- Manifest Validation
- Spirent NFVI/VIM onboard of TCs
- RC Test Case | Req Gap Assessment - need to corroborate & close gaps
- Review April Release Deliverables
- On/by 2/14, ensure all Baldy To-Dos are captured
- Review Backlog
- Confirm Volunteer(s)
- Confirm Issue
- Prepare for Apr. agenda and topics. List possible topics proposed for Apr. CNTT workshop
- Review open PRs
- AOB
- RI/RC 2/12 Gov Slide Review
Agenda:
- Status
- Labs & Next Steps (POD10/15)
- Prior status: POD15. Continued CD failures. For next 2 weeks, perform manual deployment, analyze logs.
- Notes:
- Pod10: Access to APIs work. Horizon dashboard is still not accessible. Not sure if deployment/networking issue. Sridhar to redeploy later today.
- Pod15: Deployment failures. Need daily CNTT jobs to stop. Then, will perform manual deployment. (Cedric?)
- Manifest Validation: Awaiting approval from Airship team to start. (James?)
- HDV - finalize schema, build prototype
- Prior status: New HDV RI chapter (index) merged https://github.com/cntt-n/CNTT/pull/1022. Daniel provided overview of TripleO/Apex, and recommends potential TripleO (w/o Apex) scenario. New PR has been created by Chen Liang for the HDV contents. https://github.com/cntt-n/CNTT/pull/1050. Waiting for review from the wider community.
- Notes:
- Developer volunteers to build prototype?
- Manifest Validation - finalize schema
- Prior status:I Sridhar Rao created initial set of aspects (configuration) to validate as part of manifest (S/W) validation.
Next steps:
- James Gu - review for changes - complete?
Prototype after the review - dates?
Spirent NFVI/VIM onboard of TCs
Prior status: Repo created. Follow-up needed to onboard into Xtesting.
- Notes:
- Onboard status?
- RC Test Case | Req Gap Assessment
- Prior status: Completed. Need to corroborate and close gaps.
- Notes:
- Labs & Next Steps (POD10/15)
- Review April Deliverables
- Candidate List: CNTT Baldy
- RI Goals:
- Review Backlog & To Do - https://github.com/cntt-n/CNTT/projects/7
- Confirm Volunteer & Issues
WSL Note: Features below should be implemented in order.
Reference # | Feature | Notes | Volunteer | Related Issues |
---|---|---|---|---|
baldy.ri1.1 | General Cleanups | All Chapters | Qiao Fu | https://github.com/cntt-n/CNTT/issues/1041 |
baldy.ri1.2 | Complete Overall Requirements | Ch02 | Currently do not see any need for update. Will create issue if certain requirement been pointed out | |
baldy.ri1.3 | Complete Lab Requirements | Ch04 | Currently do not see any need for update. Will create issue if certain requirement been pointed out | |
baldy.ri1.4 | Complete Target State & Metadata | Ch03 | need careful review to see if we capture all the requirement from RM and RA. | |
baldy.ri1.5 | Complete Installer Requirements and hardware delivery requirement | Ch05 | Liang Chen | |
baldy.ri1.6 | Complete Lab Cookbook (Ops) | Ch06 | ||
baldy.ri1.6 | Restructure & Complete Integration Cookbook | Ch07 | ||
baldy.ri1.7* | Implement Profiles within OPNFV Installers and consume CNTT metadata | DEV | Lincoln Lavoie Sridhar Rao | This work depends on the on-going activity and discussion of information model in OPNFV. create one issue to follow this work |
c. RC Goals:
- Review backlog, and To-Do: https://github.com/cntt-n/CNTT/projects/4
- Confirm Volunteer & Issues
WSL Note: Features below should be implemented in order.