  1. The goal of the MVP is to specify a suite of VNF validation tests and associated test infrastructure that can be developed within the time-frame of the E-release of ONAP.
  2. Tests will focus on on-boarding and instantiation of the VNF in/within ONAP.
  3. Tests will focus on HEAT based VNFs. (focus exclusively?)
  4. Test will leverage the SDNC and APPC controllers.
  5. Tests will use the the VIM that is provided with ONAP i.e. a generic version of OpenStack. (a future program update / release may migrate to other VIMs).
  6. VNFs are validated against the specific release of ONAP (i.e. VNF is validated against ONAP E-release or F-release).
  7. VNFs must also past the current VNF criteria defined by ONAP for the initial release of VNF compliance testing.
  8. Testing uses existing interfaces into ONAP for stimulus / response to "drive" the tests (i.e. avoid creating new requirements / interfaces for the ONAP at large project).

...

  1. Tests can readily be run, with high level of repeatability.
  2. Level of complexity is manageable by end users (i.e. ease of ONAP deployment + test cases).

Timeline

DateDeliverable
April 19, 2019MVP agreed by the CVC.
April 23, 2019Presentation of MVP to LFN EUAG during teleconference
End AprilMVP agreed / finalized (feature freeze)
Late April / Early MayMeetings with development/technical teams to determine what currently exists and what needs to be proposed as new work.
Late MayDevelopment plans finalized with technical teams.
June 13, 2019ONAP E-release M1
June - JulyVNF requirements created for life-cycle
July 18, 2019ONAP E-release M2/M3
JulyTest case development, per requirements set
AugustTest tooling development
August 29, 2019ONAP E-release
SeptemberBeta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only
OctoberBeta conclusions, first VNFs publicly listed as passing the validation testing