Date | Deliverable | |
---|---|---|
April 19, 2019 | MVP agreed by the CVC. | |
April 23, 2019 | Presentation of MVP to LFN EUAG during teleconference | |
End April | MVP agreed / finalized (feature freeze) | |
Late April / Early May | Discussions with ONAP Integration Team to understand what exists for testing today,Meetings with development/technical teams to determine what currently exists and what needs to be | developed.proposed as new work. |
Late May | Development plans finalized with technical teams. | |
June 13, 2019 | ONAP E-release M1 | |
June - July | VNF requirements created for life-cycle | |
July 18, 2019 | ONAP E-release M2/M3 | |
July | Test case development, per requirements set | |
August | Test tooling development | |
August 29, 2019 | ONAP E-release | |
September | Beta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only | |
October | Beta conclusions, first VNFs publicly listed as passing the validation testingNeed to insert ONAP E-release mile-stones here. |