  1. The goal of the MVP is to develop validation testing within the time-frame of the E-release of ONAP.
  2. Tests will focus on on-boarding and instantiation of the VNF in/within ONAP.
  3. Tests will focus on HEAT based VNFs.
  4. Test will leverage the SDNC and APPC controllers.
  5. Tests will use the the VIM that is provided with ONAP (a future program update / release may migrate to other VIMs).
  6. VNFs are validated against the specific release of ONAP (i.e. VNF is validated against ONAP E-release or F-release).
  7. VNFs must also past the compliance testing (i.e. testing defined in the initial release of VNF testing).
  8. Testing uses existing interfaces into ONAP for stimulus / response to "drive" the test (i.e. avoid creating new requirements / interfaces for the ONAP at large project).

What is needed / Work to do

  1. ONAP release must be readily deploy-able, to allow a test framework to run on the deployment to test a VNF.  
    1. Will ensure VNF tests are conducted in a uniform environment.
  2. Definition of life cycle requirements (i.e. what the test cases validate)
    1. Does instantiation include configuration?
    2. Does instantiation include health check?
  3. Test case description template for VNF validation work
  4. Definition of the set of ONAP components required for the testing (ONAP profile used for testing).
  5. Definition of requirements needed for testing (i.e. hardware / pod requirements to run testing).
  6. Test tooling that drives testing through existing ONAP interfaces.

Open Questions

  1. Can the test requirements or definitions (procedures) by pulled from, or reuse, the ETSI TST-0007
  2. What are the integration and testing interfaces that are currently available, i.e. used by the integration team / gating team?

Definition of Done / Success Measures

  1. Tests can readily be run, with high level of repeatability.
  2. Level of complexity is manageable by end users (i.e. ease of ONAP deployment + test cases).

Timeline

DateDeliverable
April 19, 2019MVP agreed by the CVC.
April 23, 2019Presentation of MVP to LFN EUAG during teleconference
Early MayDiscussions with ONAP Integration Team to understand what exists for testing today, and what needs to be developed.

Need to insert ONAP E-release mile-stones here.