# | item | HEAT specifics | exist? | resources needed | TOSCA specifics | exist? | resources needed | |||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Update VNFREQTS for LCM definition | ??? | 70% | 50% | Requirements for VNF "life-cycle" will be the same for HEAT / TOSCA. | 70% | VNFREQTS Team | Requirements for VNF "life-cycle" will be the same for HEAT / TOSCA. | 50% | VNFREQTS Team | ||
2 | Automation Script(s) to on-board VSP | Integration TestSuite | Yes | Contributions to Integration project by VVP team. | Victor: Investigating to reuse the existing scripts. | ~80% | VNFSDK Team | |||||
3 | Automation Script(s) to Create VF | Integration TestSuite | Yes | Contributions to Integration project by VVP team. | Victor: Investigating to reuse the existing scripts. | ~80% | VNFSDK Team | |||||
4 | Automation Script(s) to Create Service | Integration TestSuite | Yes | Contributions to Integration project by VVP team. | Victor: Investigating to reuse the existing scripts. | ~80% | VNFSDK Team | |||||
5 | 5 | Automation Script(s) to Pre-Load Image | Integration TestSuite | Yes | 6 | Automation Script(s) to Submit Preloads | Integration TestSuite | Yes | Contributions to Integration project by VVP team. | SDN-C Specific Operation: TOSCA could be ignored | N/A | |
78 | Automation Script(s) to Instantiate VNF | Integration TestSuite | Yes | Contributions to Integration project by VVP team. | Need to develop new scripts | No | VNFSDK Team | |||||
89 | Automation Script(s) to Healthcheck VNF | N/A - not planned for this phase | N/A | Nice to have | N/A | |||||||
9 | Clean up after test(s) | Implemented directly in TestSuite | TestSuite Team | Implemented directly in TestSuite | TestSuite Team |
Open Questions
- Can the test requirements or definitions (procedures) by pulled from, or reuse, the ETSI TST-0007
- What are the integration and testing interfaces that are currently available, i.e. used by the integration team / gating team?
...
Date | Deliverable |
---|---|
April 19, 2019 | MVP agreed by the CVC. |
April 23, 2019 | Presentation of MVP to LFN EUAG during teleconference |
End April | MVP agreed / finalized (feature freeze) |
Late April / Early May | Meetings with development/technical teams to determine what currently exists and what needs to be proposed as new work. |
Late May | Development plans finalized with technical teams. |
June 13, 2019 | ONAP E-release M1 |
June - July | VNF requirements created for life-cycle |
July 18, 2019 | ONAP E-release M2/M3 |
July | Test case development, per requirements set |
August | Test tooling development |
August 29, 2019 | ONAP E-release |
September | Beta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only |
October | Beta conclusions, first VNFs publicly listed as passing the validation testing |
External Resources
https://wiki.onap.org/display/DW/OVP+LCM+Support