#itemHEAT specificsexist?resources neededTOSCA specificsexist?resources needed
1Update VNFREQTS for LCM definition???70%50%Requirements for VNF "life-cycle" will be the same for HEAT / TOSCA.70%VNFREQTS TeamRequirements for VNF "life-cycle" will be the same for HEAT / TOSCA.50%VNFREQTS Team
2Automation Script(s) to on-board VSPIntegration TestSuiteYesContributions to Integration project  by VVP team.Victor: Investigating to reuse the existing scripts.~80%VNFSDK Team
3Automation Script(s) to Create VFIntegration TestSuiteYesContributions to Integration project  by VVP team.Victor: Investigating to reuse the existing scripts.~80%VNFSDK Team
4Automation Script(s) to Create ServiceIntegration TestSuiteYesContributions to Integration project  by VVP team.Victor: Investigating to reuse the existing scripts.~80%VNFSDK Team
55Automation Script(s) to Pre-Load ImageIntegration TestSuiteYes6Automation Script(s) to Submit PreloadsIntegration TestSuiteYesContributions to Integration project  by VVP team.SDN-C Specific Operation: TOSCA could be ignoredN/A
78Automation Script(s) to Instantiate VNFIntegration TestSuiteYesContributions to Integration project  by VVP team.Need to develop new scriptsNoVNFSDK Team
89Automation Script(s) to Healthcheck VNFN/A - not planned for this phaseN/A
Nice to haveN/A
9Clean up after test(s)Implemented directly in TestSuite
TestSuite TeamImplemented directly in TestSuite
TestSuite Team


Open Questions

  1. Can the test requirements or definitions (procedures) by pulled from, or reuse, the ETSI TST-0007
    1. What are the integration and testing interfaces that are currently available, i.e. used by the integration team / gating team?

...

DateDeliverable
April 19, 2019MVP agreed by the CVC.
April 23, 2019Presentation of MVP to LFN EUAG during teleconference
End AprilMVP agreed / finalized (feature freeze)
Late April / Early MayMeetings with development/technical teams to determine what currently exists and what needs to be proposed as new work.
Late MayDevelopment plans finalized with technical teams.
June 13, 2019ONAP E-release M1
June - JulyVNF requirements created for life-cycle
July 18, 2019ONAP E-release M2/M3
JulyTest case development, per requirements set
AugustTest tooling development
August 29, 2019ONAP E-release
SeptemberBeta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only
OctoberBeta conclusions, first VNFs publicly listed as passing the validation testing

External Resources

https://wiki.onap.org/display/DW/OVP+LCM+Support

Testing framework comparison