DateDeliverable
April 19, 2019MVP agreed by the CVC.
April 23, 2019Presentation of MVP to LFN EUAG during teleconference
End AprilMVP agreed / finalized (feature freeze)
Late April / Early MayMeetings with development/technical teams to determine what currently exists and what needs to be proposed as new work.
Late MayDevelopment plans finalized with technical teams.
June 13, 2019ONAP E-release M1
June - JulyVNF requirements created for life-cycle
July 18, 2019ONAP E-release M2/M3
JulyTest case development, per requirements set
AugustTest tooling development
August 29, 2019ONAP E-release
SeptemberBeta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only
OctoberBeta conclusions, first VNFs publicly listed as passing the validation testing