EventDatesRelative DatesStart Relative DatesDescription
Release Start2022-05XX-24XXStart DateStart DateDeclare Intention: Submit Project Proposal (for new projects) and Project Plan in wiki under projects.
Initial Checkpoint2022-06XX-07XXStart Date + 2 WeeksStart Date + 2 WeeksInitial Checkpoint. All Projects must have completed project plan and get the plan reviewed under TSC meeting.
Integrated Projects deadline2022-06XX-21XXInitial Checkpoint + 2 WeeksStart Date + 6 WeeksAs this is the first release, this is the period for each project to confirm the version of the projects they want to integrate and they are available to be correctly consumed. Deadline for the confirmation.
CSIT



Middle Checkpoint2022-09XX-13XX
Start Date + 16 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze2022-10XX-11XXMiddle checkpoint + 4 WeeksStart Date + 20 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint2022-10XX-25XXCode Freeze + 2 WeeksStart Date + 22 WeeksFinal Checkpoint for all project.
Formal Release2022-11-15XX6 X months after start dateStart Date + 6 X monthsFormal Release for XGVela.

...