The first XGVela release plans to be delivered in 2022. Duration will last for 6 months.


EventDatesRelative DatesStart Relative DatesDescription
Release Start2022-05-24Start DateStart DateDeclare Intention: Submit Project Proposal (for new projects) and Project Plan in wiki under projects.
Initial Checkpoint2022-06-07Start Date + 2 WeeksStart Date + 2 WeeksInitial Checkpoint. All Projects must have completed project plan and get the plan reviewed under TSC meeting.
Release Integrated deadline2022-06-21Initial Checkpoint + 2 WeeksStart Date + 6 WeeksDeadline for Release Integrated Projects to provide the desired version deliverables for downstream Snapshot Integrated Projects to consume.
Middle Checkpoint2022-09-13
Start Date + 16 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze2022-10-11Middle checkpoint + 4 WeeksStart Date + 20 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint2022-10-25Code Freeze + 2 WeeksStart Date + 22 WeeksFinal Checkpoint for all project.
Formal Release2022-11-156 months after start dateStart Date + 6 monthsFormal Release for XGVela.

...


How to prepare key contents of each event

...

? Please go to Release Process.