# | Task Description | Dpndcy | Dur. | Sched. Start | Act. Start | Sched. End | Act. End | Resources/ Responsible | Issues (GitHub Link) | Comments/Notes |
---|---|---|---|---|---|---|---|---|---|---|
1 | Secure Lab resources
| I-6 | 0 | 4/20 | 5/11 | 5/15 | 6/5 | |||
2 | VI Lab Standup
| E-1 SS +2d | 5d | 4/22 | 6/8 | 5/22 | Orange is always ready AT&T Setup completed on 6/3 Mirantis is working with UNH to be ready the week of 6/15 | |||
3 | Test Case Execution
| E-2 | 4d | 6/1 | 6/1 | 6/12 | ||||
4 | Data collection | E-3 | 5d | 5/29 | 6/522 | |||||
5 | ETSI PlugTest Infrastructure | E-1 | 5d | 5/45/8 | CANCELLED | |||||
6 | ETSI PlugTest | E-5 | 5d | 6/15 | 6/19 | ETSI VNF participants | CANCELLED |