AOB

=========================================================

...


  • RC Work stream
    • RC NFVI: Rajesh, Mike
      • Documentation moving along?  Ch's 1,2,3,4
      • Issues
      • PRs
      • Status | Tasks (Work in progress)
        •  Receive Lab (date)
        •  (In progress) Translate RA requirements to Manifest Needs (See above for Assistance needed)
        •  Tune Manifest to match RA requirements (Target End State Lab - POD15) - status of POD 10, then date for POD 15
        •  Testing
          1. Prepare automation harness - connectivity, validation (POD10)? – Cedric?
            1. e.g. functest-smoke-cntt was just created. neutron-tempest-plugin-api is already conformed with the current API section.
          2. Create Test Plan
          3. Finalize Test Harness/Framework
          4. Perform Manifest Validations
          5. Results Collection & Normalization
    • RC VNF:  Mike
      • Documentation moving along?  Ch's 5,6,7
      • Issues
      • PRs
      • Status | Tasks (Work in progress)
        1. VNF Prototypes
          •  (In Progress) Families Identified
          •  (In Progress) Test Requirements Identified
          •  

            Strategy

            1. Use POD10 for Network Intensive. 

            2. Measure stats related to the NFVi datapath capacity.

            3. Goal will be to demonstrate full automation of the environment (continuous deployment) with test cases with some useful test results (continuous testing).
            4. Status? Then look at adding compute and storage intensive VNFs and identify test cases that map back to CNTT specified capabilities.(Luc, Sridhar, Al, Trevor - creating more detailed plan?).
        2. Testing
          1. Create Test Plan
          2. Finalize Test Harness/Framework
          3. Results Collection & Normalization
    • RC Dev: Cedric
      • Documentation moving along?  Ch's 8,9,10,11
      • Issues
      • PRs
      • Status | Tasks (Work in progress)
        • Jenkins setup
        • VNF prototype
          1.  Development
          2. Connectivity to POD15

...