Work Items


High Level Work Plan and Contributors


ItemDescriptionProject/TeamContributorsNotesStatusDeadline
1

Common VNF validation LCM requirements

VNFRQTS

Steven Wright - AT&T

Work is stated: https://docs.onap.org/en/latest/submodules/vnfrqts/testcases.git/docs/index.html


This must be done in the E-release, if we are going to "Point" to an ONAP release for a Badge'd VNF.

2

Common Library of Commands/Functions

Integration


This depends on items 4 & 5.



3

HEAT Specific requirements for VNF validation

VNFRQTS




4

HEAT VNF Validation test cases

VVPhttps://wiki.onap.org/display/DW/OVP+LCM+Support#OVPLCMSupport-HowHeatbasedVNFisinstatiated

5

HEAT specific commands/funcs

Integration

https://github.com/onap/integration/blob/master/test/hpa_automation/heat/hpa_automation.py



6

TOSCA specific req for VNF validation.

VNFRQTS

Weitao Gao - Huawei




7

TOSCA VNF validation test case

VNFSDK/VTP

Rabi Abdel - Vodafone

Weitao Gao - Huawei

https://wiki.onap.org/display/DW/OVP+LCM+Support#OVPLCMSupport-HowTOSCAbasedVNFisinstatiated



8

TOSCA specific commands/func

Integration

Weitao Gao - Huawei

https://github.com/onap/integration/blob/master/test/hpa_automation/tosca/hpa_automation.py



9Dovetail / Portal IntegrationDovetail

Georg Kunz- Ericsson

Dan Xu - Huawei




Action Items

  •  Heather Kirksey Need to update / reach out to participants for the CVC / MVP call, which meets every other week, Monday morning.

Discussion points from DDF Event Discussions

  1. VFC Implementations - need to define the specific requirements for this first release 
  2. Need to define the test environment, including how OpenStack is deployed, and how ONAP is deployed "on top" of that NFVI
    1. Possible integration with XCI work and activities?
  3. VNFRQTS has a test case description for Instantiation in read the docs: https://docs.onap.org/en/latest/submodules/vnfrqts/testcases.git/docs/index.html
    I would invite proponents of the various TOSCA paths that Eric mentioned to document them there as well.

    1. What are the life-cycle operations that need to be worked on.
    2. Other tests? Security port scans, health checks, configuration - Need to clarify what will be in scope of the MVP, and what will be for the next release.
  4. Integration/Testsuite: No need to do anything specific to support HEAT VNF Validation.
  5. How are tests "run" from both the certification tooling, but also from the ONAP portal(s), as part of the life cycle requirements discussion

Appendix