- Feedback from CMCC: The VNFD we are using in our company are all TOSCA-based. Also, we are using VFC for VNF LCM. We suggest to update the 3rd item and the 4th item in "Requirements & Deliverables" to "Tests will focus on HEAT based VNFs and TOSCA based VNFs" and "Test will leverage the SDNC, APPC and VFC controllers".
- Verizon feedback: As mentioned in the comment below we we are using TOSCA based VNF-D as well. We would like to extend the requirements to include SOL004/SOL001 VNFs using the SDC→SO→SOL003 Adapter → External VNFM→VNF path or the SDC → SO → SOL005 Adapter → VF-C → VNF path.
- China Telecom Feedback:We have both HEAT based and TOSCA based VNFDs in the DEMO running on our testbed. It will be great if TOSCA based VNFs could be added in the Requirement, providing the resources are available.
Timeline
Date | Deliverable |
---|---|
April 19, 2019 | MVP agreed by the CVC. |
April 23, 2019 | Presentation of MVP to LFN EUAG during teleconference |
End April | MVP agreed / finalized (feature freeze) |
Late April / Early May | Meetings with development/technical teams to determine what currently exists and what needs to be proposed as new work. |
Late May | Development plans finalized with technical teams. |
June 13, 2019 | ONAP E-release M1 |
June - July | VNF requirements created for life-cycle |
July 18, 2019 | ONAP E-release M2/M3 |
July | Test case development, per requirements set |
August | Test tooling development |
August 29, 2019 | ONAP E-release |
September | Beta testing from E-release, requirements frozen / completed, test case and tooling bug fixes only |
October | Beta conclusions, first VNFs publicly listed as passing the validation testing |
...