EventDatesRelative DatesStart Relative DatesDescription
Release Start
Start DateStart Date

Declare Intention.

For new project:

  1. Submit a new project proposal following the steps on Project Proposals. Contents about "Release Planning & Release Notes" is required.
  2.  Review candidate features in Projects page and clarify the whether the features new project wants to deliver is within the list or out of the list.
  3. Review delivered features of Approved Projects to avoid duplication.

For existing project:

  1. Update "Release Planning & Release Notes" section in your project page by adding features to be delivered in new release on the section top.
Initial Checkpoint
Start Date + 2 WeeksStart Date + 2 Weeks

Initial Checkpoint.

  1. All Projects must have completed project proposal or new release plan.
  2. All projects
apply for TSC review through
  1. ' PTL should send email to xgvela-tsc@lists.xgvela.org
  1. get rlease plan publicly reviewed.
  2. PTLs of new projects will be invited to TSC meetings for project introduction. TSC will vote for new project approval.

Integrated Projects deadline


Initial Checkpoint + 2 3 WeeksStart Date + 4 5 WeeksPrevious release or other project integration for development preparation

Dependency checkpoint.


Middle Checkpoint
Integrated projects deadline + 8 9 weeksStart Date + 12 14 WeeksMiddle Checkpoint for progress of all Projects.
Code Freeze
Middle checkpoint + 4 WeeksStart Date + 16 18 WeeksCode freeze for all Projects - cut and lock release branch. 
Final Checkpoint
Code Freeze + 4 WeeksStart Date + 20 22 WeeksFinal Checkpoint for all project. Documentation should be completed before final checkpoint.
Formal Release
Final checkpoint + 2 WeeksStart Date + 22 24 WeeksFormal Release for XGVela.

...